The finished product!
August 2, 2008
Landscaping and Spring!
April 28, 2008
Under Matt Ulrich of Matthew Ulrich Landscape Design’s direction, the landscape installation has been taking beautiful shape. The larger part of the brick patio is being constructed reusing brick from the existing site. All other masonry stone was selected from a local stone yard less than a half mile away.
In the foreground, the perimeter of the rain garden can be seen. Both site surface and subsurface water will be diverted here, and the rain garden will soon be planted with native perennials which will attract birds and butterflies. The plantings will be able to tolerate wet conditions, but will also be drought tolerant, requiring no additional watering. The rain garden will treat the water and allow it to drain slowly back into the water table, reducing the addition of contaminants to nearby Pentucket Pond.
Used granite curbing recycled from a public works project in Lawrence was used for the granite steps leading to the new entry. 
Installation of the parking court is underway. A large slab of granite was split and is being used as entry pillars for the court.
Installation of parking court and brick walkway. Beyond, the house is ready for final stucco patching and paint.
Found beach rock at the base of the stone retaining wall allows water to penetrate to a drain below.
A welcoming entry
February 11, 2008

While interior rough-ins and insulation work are underway, Meadowview built and installed the new GreenBridge-designed entry overhang, which offers a welcoming and protected entry.
Moving Along!
January 11, 2008

The slab has been poured and the addition is taking shape.

Rigid insulation is on the inside of the foundation under the windows.

Marie Klien from Samarra Studios paints over the newly insulated Great Room ceiling and exposed beams using Benjamin Moore’s Aura, low VOC paint.
Insulation and heating
January 5, 2008

Tubing installed for the in-slab radiant heating system over metal slab reinforcement and reflective 2″ rigid insulation. Radiant heat is more efficient than baseboard heating because the boiler heats circulating water to a lower temperature, the heat is dispersed throughout the space and not just the perimeter, and the floor material (concrete here) stores the heat better than air.

2″ of rigid insulation added between the structural beams in the Great Room. Mike Brown estimates that this increase of R-value by 10 will save $150 in heating costs annually.
Ripped up floor and rough-ins!
December 12, 2007
This picture is facing what will be the new laundry room – (It’s going to be STUNNING! Really!) The slab has been removed to allow for new under-slab insulation and heat. Rough plumbing is in place for the washer and dryer – the yellow pipe is the propane line. The cats (not seen in the picture) are eagerly waiting for the installation of their new fully-insulated cat door….
Meadowview has installed the end rafter so we can now see the roof pitch for the new addition. We have taken care to keep the roof an adequate distance from the existing window sills. The new roof will be copper that will naturally ‘patina’ in place.
Detail of the lumber stamp – all the wood for the project is FSC certified and is being purchased from Sterritt Lumber Supply- Sterritt is one of the few local yards carrying FSC certified lumber and other sustainable and recycled products. This lumber is from Pleasant River in Maine – part of our goal of buying green and local - with the added bonus of seeing our flag on each piece of lumber!
Demoliton and Foundation
November 22, 2007
Foundation installed at the location of the new bay, which will be large enough for an eating area and a comfortable chair with a side table. The surveying equipment is being used to determine existing and new slopes of the ground adjacent to the building to avoid ponding and freezing near the house. Matthew Ulrich Landscape Design is working on a patio plan that may include a rain garden to take advantage of excess water at this location.
Foundation detail showing rigid insulation, sill seal under the ’sill’ wood plate and connection with old foundation. The new floor slab will be on top of 2″ rigid insulation and will sit on the concrete ’shelf’. The taller part of the foundation protects the interior from the high ground on the outside. Our client agreed to the added value option of removing the existing concrete slab in the kitchen (old garage) for the installation of a new concrete slab with insulation and radiant heat throughout.
Great example of the mysteries uncovered during demolition – this structure is at the center of what will be the new bay. We learned that the existing opening at what used to be garage doors, is being held up by a large concrete beam. Structural engineers Ross Engineering worked hard to quickly engineer a beam and connection detail to allow removal of this post.
During this team meeting, lmk interiors, ltd. reviewed the interior finish selections and equipment that have so far been selected with the client. These selections include Energy Star labeled appliances, water-saving plumbing fixtures, American Clay wall finishes, concrete or recycled product countertops, Terra Green recycled floor and wall tiles and cabinetry built with FSC certified lumber.
Advance Building Analysis’ report and findings were reviewed. The report gives suggested energy-saving modifications and annual expected cost-savings for each for a combined possible energy savings of $2700 per year!!Meadowview Construction will determine their costs to complete the energy-saving modifications to the home, with hopes of incorporating these changes into the work.
Project Startup
November 9, 2007
Our team is thrilled to be working on this beautiful circa 1930’s Spanish Tudor house and its surrounding landscape in Georgetown, Massachusetts. The immediate project consists of the removal of an existing bay on this north elevation and the additon of an eating area bay and involves interior remodeling including the Kitchen, Foyer and new Office, Laundry and Bath rooms. The client is intent to include ecofriendly design, materials and methods into the project and brings her own environmental knowledge to the team. Besides GreenBridge Architects, the project team also includes lmk interiors, ltd. , Matthew Ulrich Landscape Design and Meadowview Construction.
We brought Mike Brown from Advanced Building Analysis in before demolition began to create an energy model of the existing house. Here he is firing up his blower door test. With this and his infrared testing, he will look at insulation values of the different components of the building envelope, the walls, windows, doors as well as openings in the construction that may not be apparent to the homeowners. His analysis will give us prioritized suggestions for improving the home’s energy consumption. These work items can be included in the scope of the work for the addition to increase efficiency of the entire house.
First weekly site visit to look at newly exposed existing construction and a great recycling center. Meadowview Construction is approaching the project with great care and planning – all geared toward responsibility to the homeowners and to the environment.









